From Fedora Project Wiki
(2 intermediate revisions by the same user not shown) | |||
Line 56: | Line 56: | ||
* Could we do any sanity testing before publishing images to make sure they boot to save bandwidth and turn around time? In the case of Test Compose #1 it fell over right way. | * Could we do any sanity testing before publishing images to make sure they boot to save bandwidth and turn around time? In the case of Test Compose #1 it fell over right way. | ||
* Kevin Kofler suggests it may ultimately have worked out better simply to delay the Alpha freeze and leave dist-f14 tag open until the major problems were resolved | * Kevin Kofler suggests it may ultimately have worked out better simply to delay the Alpha freeze and leave dist-f14 tag open until the major problems were resolved | ||
|| | || We don't see any specific actions that can be taken at this time. Hopefully good lessons were learned from this experience so that they are not repeated. | ||
|- | |- | ||
|| Feature Submission Deadline || 2010-07-13 || | || Feature Submission Deadline || 2010-07-13 || | ||
Line 126: | Line 125: | ||
|- | |- | ||
|- | |- | ||
| New FI task: Hide -Alpha and -Beta releases || 2010-11-02 || MirrorManager task to hide version-Alpha and -Beta from the mirror lists on release day || || | | New FI task: Hide -Alpha and -Beta releases || 2010-11-02 || MirrorManager task to hide version-Alpha and -Beta from the mirror lists on release day || || Added an additional Release Engineering ticket to for the final release to: [[Release_Engineering_Release_Tickets#Final]] | ||
|- | |- | ||
<!-- | Task || Date || What Happened? || What To Do Differently Next Time? --> | <!-- | Task || Date || What Happened? || What To Do Differently Next Time? --> |
Latest revision as of 19:01, 24 November 2010
Could Have Been Better
Task | Date | What Happened? | What To Do Differently Next Time? | Actions Taken |
---|---|---|---|---|
Create Installable Images for QA testing #1 | 2010-07-08 |
|
|
|
Create Installable Images for QA testing #3 | 2010-07-22 |
|
|
Keep in mind for the future. |
Fedora 14 Blocker Meetings are already taking a minimum of an hour | 2010-07-24 |
|
|
Continue to look for ways to streamline meetings. By the end of the release cycle the current approach seemed to still be the best, though not perfect. |
Branch Fedora 14 | 2010-07-27 |
|
|
Keep an eye to see if this a reoccurring problem in Fedora 15 |
Fedora 14 Alpha Test Compose | 2010-07-29 |
|
|
We don't see any specific actions that can be taken at this time. Hopefully good lessons were learned from this experience so that they are not repeated. |
Feature Submission Deadline | 2010-07-13 |
|
| |
Nightly Spin composes | 2010-07-* |
|
|
|
Nightly Spin ISOs for Alpha | 2010-08-24 |
|
|
Investigate current policy around dependency issues in stable and discuss policy changes (if applicable) with FESCo. |
Notify mirrors about new release content | 2010-08-23 |
|
|
|
Web content change for F14 Alpha | 2010-08-24 |
|
|
|
Meeting times | 2010-08-31 |
|
|
|
Compose Beta RC | 2010-09-16 | RC compose was not ready until the end of 2010-09-17 because of two un-resolved blocker bugs (anaconda and kernel). Both bugs had been open for several days. | Determine if one week is really enough time from the creation of the Test Compose and and the compose of the Release Candidate. During this one week period we are supposed to test the Test Compose, identify bugs, and fix all blocker bugs, so the compose of the Release Candidate can begin. | Pulled Test Compose in by two days--instead of starting on Thursday, have Release Engineering create two days earlier (Tuesday). The result is that testing will happen earlier too. poelcat 20:53, 23 November 2010 (UTC) |
Building new spin-kickstart packages | 2010-10-12 | With the new updates policy we can't get the updated package into stable on freeze day unless we have more lead time. | Since there is already a plan to do an update if there is any change during the freeze, it isn't a big deal to do the package builds 8 days earlier. The branch before the GA freeze should stay aligned with that package build and also move 8 days earlier. (After looking more closely the spin freeze is 7 days before the final change deadline and maybe we don't need a full 8 days more.) | Ask for clarification on spins mailing. It is unclear what the specific changes should be made to the schedule. |
Testing live spins | 2010-10-22 | While I (bruno) didn't get some stuff done in time this time around, trying to go through test cases at the RC phase is too late. | If we do spins the same for F15, we need to have the mandatory testing to be done by spin owners sync'd up with the TC phase, so that we have time to react. |
|
Final Release Readiness Meeting | 2010-10-18 | Key team leads did not attend or came very late: Design, Release Engineering, Infrastructure, and Websites. | Touch base with attendees personally and ask they that send an alternate if they cannot attend. | |
New FI task: Hide -Alpha and -Beta releases | 2010-11-02 | MirrorManager task to hide version-Alpha and -Beta from the mirror lists on release day | Added an additional Release Engineering ticket to for the final release to: Release_Engineering_Release_Tickets#Final |