From Fedora Project Wiki
m (Updated agenda) |
m (Updated notes) |
||
Line 28: | Line 28: | ||
* 2010-04-01 - [[Test_Day:2010-04-01_ABRT|ABRT Test Day]] -- [[User:kparal|kparal]] | * 2010-04-01 - [[Test_Day:2010-04-01_ABRT|ABRT Test Day]] -- [[User:kparal|kparal]] | ||
* 2010-04-08 - [[Test_Day:2010-04-08_Virtualization|Virtualization Test Day]] -- [[User:jforbes|jforbes]] + [[User:mdoyle|mdoyle]] | * 2010-04-08 - [[Test_Day:2010-04-08_Virtualization|Virtualization Test Day]] -- [[User:jforbes|jforbes]] + [[User:mdoyle|mdoyle]] | ||
== Open discussion - <Your topic here> == | == Open discussion - <Your topic here> == |
Revision as of 15:47, 29 March 2010
Attendees
People present (lines said)
Regrets:
Agenda
- Proposed meeting agenda
- [FIXME MeetBot summary]
Previous meeting follow-up
- wwoods and adamw to discuss tooling needs for priv esc. test
- maxamillion will work on second draft of provenpackagers proposal
- adamw will provide a draft for the update test plan
- jlaska to post meeting time change request to test@l.fp.org
Fedora 13 test status
Upcoming test milestones:
- 2010-03-25 - Test Beta 'Release Candidate' - INPROGRESS
- 2010-03-31 - Beta Go/No-Go Meeting (20:00 EST)
Upcoming test days:
- 2010-03-30 - SSSD by default Test Day -- jlaska
- 2010-04-01 - ABRT Test Day -- kparal
- 2010-04-08 - Virtualization Test Day -- jforbes + mdoyle
Open discussion - <Your topic here>
Adjust meeting time?
Kparal and jskladan asked whether the QA meeting time could adjust to keep the localtime the same, but change UTC. This would moving the meeting from 16:00 UTC to 15:00 UTC during spring+summer. No objections were made during the meeting, jlaska would raise the topic on the list as well.
Upcoming QA events
- 2010-01-21 - Pre-Alpha Rawhide Acceptance Test Plan #1
- 2010-01-28 - Pre-Alpha Rawhide Acceptance Test Plan #2
- 2010-02-04 - Pre-Alpha Rawhide Acceptance Test Plan #3
- 2010-02-04 - NFSv4 Test Day
- 2010-02-05 - Alpha Blocker Meeting (F13Alpha) #1 (recap)
- 2010-02-11 - Test Alpha 'Test Compose' (boot media testing)
- 2010-02-12 - Alpha Blocker Meeting (F13Alpha) #2 (recap)
- 2010-02-12 - Alpha Test Candidate verification (announcement)
- 2010-02-18 - Alpha Release Candidate verification
- 2010-02-18 - Color Management test day
- 2010-02-19 - Alpha Blocker Meeting (F13Alpha) #3 (recap)
- 2010-02-24 - Alpha Go/No-Go Meeting (20:00 EST)
- 2010-02-25 - Yum Langpack plugin test day
- 2010-03-10 - Pre-Beta Acceptance Test Plan #1
- 2010-03-12 - Beta Blocker Meeting (F13Beta) #1 (recap)
- 2010-03-18 - Gnome Disk Utility Storage Test Day
- 2010-03-18 - Test Beta 'Test Compose' DELAYED
- 2010-03-19 - Beta Blocker Meeting (F13Beta) #2 (recap)
- WE ARE HERE
- 2010-03-25 - Test Beta Candidate
- 2010-03-25 - Printing Test Day
- 2010-03-26 - Beta Blocker Meeting (F13Beta) #3
- 2010-03-30 - SSSD by default Test Day
- 2010-03-31 - Beta Go/No-Go Meeting (20:00 EST)
- 2010-04-01 - ABRT Test Day