(updating to new +30 days schedule)
(updating schedule as per discusison http://lists.fedoraproject.org/pipermail/summer-coding-discuss/2010-June/000127.html)
Line 18: Line 18:
{{admon/note|Proposals may have a modified schedule included.}}
{{admon/note|Proposals may have a modified schedule included.}}
* July
* July
*: ''5 July - Midterm evaluations period begins''
*: ''05 July - Midterm evaluations period begins''
*: '''12 July - Midterm evaluations due'''
*: ''05 July - Student midterm deadline for evaluation (first, soft deadline)''
*: '''08 July - Student midterm deadline for evaluation (final deadline)'''
*: ''12 July - Midterm evaluations due from mentors''
* August
* August
*: '''09 August - Project coding completes'''
*: '''09 August - Project coding completes'''

Revision as of 15:29, 23 June 2010

This schedule is ready for Summer Coding 2010. Join the discussion mailing list and/or watch this page to be updated about schedule changes.

Start dates are emphasized and deadlines are in bold emphasis for student items.

  • April
    7 April - Students can begin submitting applications
  • May
    Whole month - students, mentors, and sub-projects get to know each other
    13 May - Mentors need to finish idea pages
    20 May - Students applications + proposals need to be in
    21 May - Sponsors must pledge funding by this point
    24 May - Organizers finalize how many applications will be accepted
    27 May - Mentors + admins finalize rank-ordered list
    28 May - Students informed yes/no about application
  • June
    Whole month - code, interact
    01 June - Project begins (depending on proposal)
Proposals may have a modified schedule included.
  • July
    05 July - Midterm evaluations period begins
    05 July - Student midterm deadline for evaluation (first, soft deadline)
    08 July - Student midterm deadline for evaluation (final deadline)
    12 July - Midterm evaluations due from mentors
  • August
    09 August - Project coding completes
    16 August - Students final report, code snapshot, and evaluations due
    20 August - Mentor evaluations due for students
    23 August - Final evaluations due back to students
    25 August - Mentor, sub-project evaluations due
  • September
    01 September - Sponsors receive report from organizers
    06 September - Sponsors release and deliver funds (proposed date)