From Fedora Project Wiki
m (→Fedora Ambassadors Schedule: added spins to list) |
No edit summary |
||
Line 39: | Line 39: | ||
| Last date of release event and report || || One month after release | | Last date of release event and report || || One month after release | ||
|} | |} | ||
== John's Example == | |||
'''Example schedule--not real data''' | |||
{| border="1" | |||
|- style="color: white; background-color: #3074c2; font-weight: bold" | |||
| '''Task Name''' || '''Start Date''' || '''End Date''' || '''Dependencies''' | |||
|- ||||||style="color: black; background-color: #eeeff1" | |||
| Create Budget for Fedora 14 || 2010-06-21 || 2010-06-25 || n/a | |||
|- | |||
| Request Funding || 2010-06-28 || 2010-06-30 || Creating budget | |||
|- | |||
| Order Media || 2010-07-01 || 2010-07-30 || Funding approved | |||
|- | |||
| Send Media to John || 2010-08-02 || 2010-08-02 || Ordering & Receiving Media | |||
|- | |||
|} | |||
[[Category:Ambassadors]] | [[Category:Ambassadors]] |
Revision as of 15:42, 25 June 2010
Fedora Ambassadors Schedule
Task Name | Required time | Deadline |
Work with marketing for creating talking points | As per their schedule | |
Pick Featured spin to get custom DVD/CD Sleeve. | 1 week | BEGIN one week following spins freeze |
File ticket with Design team for custom DVD/CD Sleeve. | 1 day | Start/Finish Day after "Pick Featured Spin..." item. |
Send out call for release events and media production | 1 day | One and a half months before the release |
Regional meetings on Swag/media production, choose point of contact | 15 days | one month before release |
Funding request submission for swag production | - | Three weeks before release |
FAmSCo meeting for reviewing and clearing the event/swag requests | 1 | One week before the release |
Work with infrastructure for making the ISO available to Point of Contact immediately after GA staging | - | On GA staging |
Work with design for making the media/sticker artwork available | 2 days | One week |
Work with docs to get notes/handouts prepared, if required for events | 1 week | Three weeks |
Work with translate team to have docs in every language | 1 week | Three weeks |
Last date of submission of release events requiring funding | - | one week before release |
Arrange for a couple of IRC sessions for ambassadors on the new release | two classroom sessions | One week |
Work with marketing on the release events | After release | |
Last date of release event and report | One month after release |
John's Example
Example schedule--not real data
Task Name | Start Date | End Date | Dependencies |
Create Budget for Fedora 14 | 2010-06-21 | 2010-06-25 | n/a |
Request Funding | 2010-06-28 | 2010-06-30 | Creating budget |
Order Media | 2010-07-01 | 2010-07-30 | Funding approved |
Send Media to John | 2010-08-02 | 2010-08-02 | Ordering & Receiving Media |