(→FY11: fixed fy11 bug) |
No edit summary |
||
Line 2: | Line 2: | ||
{{admon/note | [[Community Architecture]] vs. Fedora | The portion of the Community Architecture budget that is spent on public, Fedora-related activities is detailed here. ''This is only a subset of the Community Architecture team's total internal-to-Red-Hat budget.''}} | {{admon/note | [[Community Architecture]] vs. Fedora | The portion of the Community Architecture budget that is spent on public, Fedora-related activities is detailed here. ''This is only a subset of the Community Architecture team's total internal-to-Red-Hat budget.''}} | ||
== Quarters == | |||
Fedora's fiscal year is split into four quarters, which run from: | |||
* March - May (Q1) | |||
* June - August (Q2) | |||
* September - November (Q3) | |||
* December - February (Q4) | |||
== FY12 == | == FY12 == |
Revision as of 21:44, 12 July 2011
The Fedora Project believes in transparency and accountability in its use of funds.
Quarters
Fedora's fiscal year is split into four quarters, which run from:
- March - May (Q1)
- June - August (Q2)
- September - November (Q3)
- December - February (Q4)
FY12
For Community Architecture expenses from March 1, 2011 - February 29, 2012 that are directly related to the Fedora Project, go here.
FY11
The accounting below is a subset of the Community Architecture budget that was spent on Fedora from March 1, 2010 - February 28, 2011.
Item | Budget | Spend |
---|---|---|
Premier Fedora Events | $80,000 | $89,980 |
Regional support | $100,000 | $82,805 |
Discretionary funds | $20,000 | $14,410 |
= | = | |
Total | $200,000 | $187,195 |
FY10
The accounting below is a subset of the Community Architecture budget that was spent on Fedora from March 1, 2009 - February 28, 2010.
Item | Q1 | Q2 | Q3 | Q4 | = | Total |
---|---|---|---|---|---|---|
Premier Fedora events | $20,000 | $20,000 | $15,000 | $20,000 | = | $75,000 |
Regional support | $32,000 | $20,000 | $20,000 | $32,000 | = | $104,000 |
Discretionary | n/a | n/a | n/a | n/a | = | n/a |
= | = | = | = | = | ||
Total budget | $52,000 | $40,000 | $35,000 | $52,000 | = | $179,000 |
Total spend | $47,110 | $43,570 | $29,795 | $45,620 | = | $166,095 |
FY09
The accounting below is a subset of the Community Architecture budget that was spent on Fedora from March 1, 2008 - February 28, 2009.
Item | Q1 | Q2 | Q3 | Q4 | = | Total |
---|---|---|---|---|---|---|
FUDCon Boston | $20,000 | = | $20,000 | |||
FUDCon Brno | $20,000 | = | $20,000 | |||
FUDCons and FADs | $20,000 | = | $20,000 | |||
Fedora @ FISL | $15,000 | = | $15,000 | |||
Fedora @ LinuxTag | $20,000 | = | $20,000 | |||
Global events & swag | $20,500 | $15,500 | $16,000 | $30,000 | = | $82,000 |
College scholarship | $2,000 | = | $2,000 | |||
LWN subscription | $1,000 | = | $1,000 | |||
Fedora in India | $8,000 | $8,000 | $9,000 | = | $25,000 | |
= | = | = | = | = | ||
Total budget | $58,500 | $43,500 | $44,000 | $59,000 | = | $205,000 |
Total spend | $54,790 | $44,675 | $32,930 | $43,070 | = | $175,465 |
FY08 and FY07
The accounting below is a summary of the Fedora Project's expenses from March 1, 2006 - February 29, 2008.
The FY08 budget was $123,500 and the amount spent was $67,025.
The FY07 budget was $108,000 and the amount spent was $76,770.
Full details are available.
Summary
The following summary is for all completed fiscal years.
Year | Spend |
---|---|
FY07 (March 1, 2006 - February 28, 2007) | $76,770 |
FY08 (March 1, 2007 - February 29, 2008) | $67,025 |
FY09 (March 1, 2008 - February 28, 2009) | $175,465 |
FY10 (March 1, 2009 - February 28, 2010) | $166,095 |
FY11 (March 1, 2010 - February 28, 2011) | $187,195 |
Total | $672,550 |