From Fedora Project Wiki
Line 6: | Line 6: | ||
{| border="1" | {| border="1" | ||
|- style="color: white; background-color: #3074c2; font-weight: bold" | |- style="color: white; background-color: #3074c2; font-weight: bold" | ||
| '''Task Name''' || ''' | | '''Task Name''' || '''Required time''' || '''Deadline''' | ||
|- ||||||style="color: black; background-color: #eeeff1" | |- ||||||style="color: black; background-color: #eeeff1" | ||
|- | |- | ||
| Work with marketing for creating talking points || As per their schedule | | Work with marketing for creating talking points || || As per their schedule | ||
|- | |- | ||
| Send out call for release events and media production || One and a half months before the release | | Send out call for release events and media production || 1 day ||One and a half months before the release | ||
|- | |- | ||
| Regional meetings on Swag/media production, choose point of contact || | | Regional meetings on Swag/media production, choose point of contact || 15 days || one month before release | ||
|- | |- | ||
| Funding request submission for swag production || Three weeks before release | | Funding request submission for swag production || - ||Three weeks before release | ||
|- | |- | ||
| FAmSCo meeting for reviewing and clearing the event/swag requests || One week before the release | | FAmSCo meeting for reviewing and clearing the event/swag requests|| 1 || One week before the release | ||
|- | |- | ||
| Work with infrastructure for making the ISO available to Point of Contact immediately after GA staging|| On GA staging | | Work with infrastructure for making the ISO available to Point of Contact immediately after GA staging||- ||On GA staging | ||
|- | |- | ||
| Work with design for making the media/sticker artwork available || One week | | Work with design for making the media/sticker artwork available || 2 days || One week | ||
|- | |- | ||
| Work with docs to get notes/handouts prepared, if required for events || Three weeks | | Work with docs to get notes/handouts prepared, if required for events|| 1 week || Three weeks | ||
|- | |- | ||
| Last date of submission of release events requiring funding || one week before release | | Last date of submission of release events requiring funding || - || one week before release | ||
|- | |- | ||
| Arrange for a couple of IRC sessions for ambassadors on the new release || One week | | Arrange for a couple of IRC sessions for ambassadors on the new release || two classroom sessions || One week | ||
|- | |- | ||
| Work with marketing on the release events || | | Work with marketing on the release events || || After release | ||
|} | |} | ||
[[Category:Ambassadors]] | [[Category:Ambassadors]] |
Revision as of 05:31, 24 June 2010
Fedora Ambassadors Schedule
Task Name | Required time | Deadline |
Work with marketing for creating talking points | As per their schedule | |
Send out call for release events and media production | 1 day | One and a half months before the release |
Regional meetings on Swag/media production, choose point of contact | 15 days | one month before release |
Funding request submission for swag production | - | Three weeks before release |
FAmSCo meeting for reviewing and clearing the event/swag requests | 1 | One week before the release |
Work with infrastructure for making the ISO available to Point of Contact immediately after GA staging | - | On GA staging |
Work with design for making the media/sticker artwork available | 2 days | One week |
Work with docs to get notes/handouts prepared, if required for events | 1 week | Three weeks |
Last date of submission of release events requiring funding | - | one week before release |
Arrange for a couple of IRC sessions for ambassadors on the new release | two classroom sessions | One week |
Work with marketing on the release events | After release |