Line 29: | Line 29: | ||
| Release event submission closes, FAmSCo review meeting, budget review/allocation || 24 sept || 0 days || Final Blocker Meeting #2 | | Release event submission closes, FAmSCo review meeting, budget review/allocation || 24 sept || 0 days || Final Blocker Meeting #2 | ||
|- | |- | ||
| All regional teams hold at least one IRC session for ambassadors on the new release || 1st | | All regional teams hold at least one IRC session for ambassadors on the new release || 1st Oct || 14 days || Final Blocker Meeting (f14blocker) #3 | ||
|- | |- | ||
| FAmSCo and regional teams meet to discuss any hitch on events/media/swag || 12 | | FAmSCo and regional teams meet to discuss any hitch on events/media/swag || 12 Oct|| 1 day || prev item | ||
|- | |- | ||
| Point of Contacts work with infrastructure for getting ISO immediately after final image is composed and available to mirrors for sync || 21 | | Point of Contacts work with infrastructure for getting ISO immediately after final image is composed and available to mirrors for sync || 21 Oct|| 3 days || Start Stage & Sync RC to Mirrors || | ||
|- | |- | ||
| Regional leads and event owners work with marketing for getting publicity for release events || 21 | | Regional leads and event owners work with marketing for getting publicity for release events || 21 Oct || 7 days || Final (GA) Release | ||
|- | |- | ||
| Release events and report for events || 26 Oct || 30 days || Final (GA) Release | | Release events and report for events || 26 Oct || 30 days || Final (GA) Release |
Latest revision as of 11:00, 26 June 2010
Fedora Ambassadors Schedule
Pass #1
Task Name | Start Date | End Date | Dependencies | |
Generic meetings involving FAmSCo, regional leads, and ambassadors on upcoming release | 26 Aug | 7 days | None | |
Call from FAmSCo and Regional teams for preparation on Media/SWAG | 26 Aug | 0 day | None | |
Regional team meetings, requirement gathering, choose point of contact for swag/media production | 27 Aug | 7 days | None | |
Funding request submission for swag/media production | 27 Aug | 7 days | None | |
Point of contacts work with the design team for media/swag/poster artwork | 6 Sept | 14 days | unsure, will check with design team | |
Call from FAmSCo and Regional teams for release events | 9 Sept | 0 day | Beta Blocker Meeting | |
Regional teams and event owners work out release event details, work out requirements and file work item tickets with various teams, and file budget requests | 9th Sept | 14 days | prev item | |
Release event submission closes, FAmSCo review meeting, budget review/allocation | 24 sept | 0 days | Final Blocker Meeting #2 | |
All regional teams hold at least one IRC session for ambassadors on the new release | 1st Oct | 14 days | Final Blocker Meeting (f14blocker) #3 | |
FAmSCo and regional teams meet to discuss any hitch on events/media/swag | 12 Oct | 1 day | prev item | |
Point of Contacts work with infrastructure for getting ISO immediately after final image is composed and available to mirrors for sync | 21 Oct | 3 days | Start Stage & Sync RC to Mirrors | |
Regional leads and event owners work with marketing for getting publicity for release events | 21 Oct | 7 days | Final (GA) Release | |
Release events and report for events | 26 Oct | 30 days | Final (GA) Release |