Attendees
People present (lines said):
Regrets:
Agenda
- [FIXME Proposed meeting agenda]
- [FIXME MeetBot summary]
Previous meeting follow-up
- jlaska + fenris02 to review whether F-13-Beta is an option for boot.fedoraproject.org
- Already completed by the infrastructure team, yay infrastructure!
See agenda below for additional follow-up items included in specific topics
Fedora 13 RC test status
Upcoming test milestones:
- 2010-04-16 - Pre-RC Branched Acceptance Test Plan -- DELAYED, now INPROGRESS
- 2010-04-23 - Final Blocker Meeting (f13blocker) #2 (recap)
- 2010-04-29 - Test 'Final' Test Compose
- 2010-04-30 - Final Blocker Meeting (f13blocker) #3
- 2010-05-05 - Final Blocker Meeting (f13blocker) #4
- 2010-05-06 - Test 'Final' RC
Upcoming test days:
- 2010-04-29 - Test_Day:2010-04-29_Preupgrade
Bodhi QA workflow status check-in
https://fedorahosted.org/bodhi/milestone/2.0
Proventesters check-in
- maxamillion - send Proventester draft to test@l.fp.org for final review
- Sent for final review at http://lists.fedoraproject.org/pipermail/test/2010-April/090252.html
- maxamillion - Request new proventester FAS group
- Requested and created (thanks lmacken) -- https://fedorahosted.org/fedora-infrastructure/ticket/2114
- https://admin.fedoraproject.org/accounts/group/view/proventesters
Package Acceptance Test Plan check-in
- kparal will bother other QA members if they have some comments to the test plan :)
- Sent for final review at http://lists.fedoraproject.org/pipermail/test/2010-April/090287.html
AutoQA check-in
There has been a lot of AutoQA activities in recent weeks, Jlaska asked the group to walk through some highlights.
Josef Skladanka updated the group on several AutoQA activities:
- Getting URLs of test results from AutoQA testruns is nearly finished. Patches out for review on autoqa-devel@lists.fedorahosted.org
- The beakerlib-based initscript test is now in production (see sample results)
- Making progress on the resultsDB - We have finished the db schema (see AutoQA_resultsdb_schema) and accepted a input API (see AutoQA_resultsdb_API)
- Next steps ...
- Prototyping the resultsdb and using an XMLRPC based API to populate with results (jlaska, 16:06:12)
- Creating a front-end which will be used for review/publish the data
Kamil Páral updated the group on his AutoQA focus areas:
- In addition to the notes above from Josef, working with Petr Splichal to automate the QA:Package_Sanity_Test_Plan (track plans using the autoqa PST milestone).
- Package Sanity ensures clean install, removal, upgrade, etc of the packages (see sample test output). There is already a 'pst' script in the repository which you can try to perform sanity tests on a downloaded package or package in a repo.
- Next steps ...
- detect that new updates are pushed to bodhi
- download the package and all relevant packages
Will Woods provide some updates on his AutoQA focus areas:
- We have enough info about current bodhi to write a bodhi update watcher, but it may have some shortcomings and will soon be obsoleted
- We have a proposed storage encoding for putting test plan metadata in the wiki (see QA:Test_Plan_Metadata_Test_Page), this will be used by the resultsdb
Open discussion - <Your topic here>
Upcoming QA events
- 2010-01-21 - Pre-Alpha Rawhide Acceptance Test Plan #1
- 2010-01-28 - Pre-Alpha Rawhide Acceptance Test Plan #2
- 2010-02-04 - Pre-Alpha Rawhide Acceptance Test Plan #3
- 2010-02-04 - NFSv4 Test Day
- 2010-02-05 - Alpha Blocker Meeting (F13Alpha) #1 (recap)
- 2010-02-11 - Test Alpha 'Test Compose' (boot media testing)
- 2010-02-12 - Alpha Blocker Meeting (F13Alpha) #2 (recap)
- 2010-02-12 - Alpha Test Candidate verification (announcement)
- 2010-02-18 - Alpha Release Candidate verification
- 2010-02-18 - Color Management test day
- 2010-02-19 - Alpha Blocker Meeting (F13Alpha) #3 (recap)
- 2010-02-24 - Alpha Go/No-Go Meeting (20:00 EST)
- 2010-02-25 - Yum Langpack plugin test day
- 2010-03-10 - Pre-Beta Acceptance Test Plan #1
- 2010-03-12 - Beta Blocker Meeting (F13Beta) #1 (recap)
- 2010-03-18 - Gnome Disk Utility Storage Test Day
- 2010-03-18 - Test Beta 'Test Compose' DELAYED
- 2010-03-19 - Beta Blocker Meeting (F13Beta) #2 (recap)
- 2010-03-25 - Test Beta Candidate
- 2010-03-25 - Printing Test Day
- 2010-03-26 - Beta Blocker Meeting (F13Beta) #3
- 2010-03-30 - SSSD by default Test Day
- 2010-03-31 - Beta Go/No-Go Meeting (20:00 EST)
- 2010-04-01 - ABRT Test Day
- 2010-04-08 - Virtualization Test Day
- 2010-04-13 - Test_Day:2010-04-13_Nouveau
- 2010-04-14 - Test_Day:2010-04-14_Radeon
- 2010-04-15 - Test_Day:2010-04-15_Intel
- 2010-04-16 - Final Blocker Meeting (f13blocker) #1 (recap)
- 2010-04-16 - Pre-RC Branched Acceptance Test Plan - DELAYED (see RHBZ #581794)
- 2010-04-22 - Test_Day:2010-04-22_StorageFiltering
- 2010-04-23 - Final Blocker Meeting (f13blocker) #2 (recap)
- WE ARE HERE
- 2010-04-29 - Test_Day:2010-04-29_Preupgrade
- 2010-04-29 - Test 'Final' Test Compose
- 2010-04-30 - Final Blocker Meeting (f13blocker) #3
- 2010-05-05 - Final Blocker Meeting (f13blocker) #4
- 2010-05-06 - Test 'Final' RC